Modernisation of the Tramway Network - Service Changes during October 2026: Line 8 fully restored
Ahead of the introduction of the new CAF Urbos trams, which will replace the historic 1940s vehicles and operate on the new tram lines currently under construction, we are upgrading the Nomentana electrical substation, which has supplied power to Rome’s tram network for many years.
The works are also allowing us to continue renewing tram tracks across the historic network and to start construction of the new tram terminus in Viale delle Milizie. The new terminus will help bring tram services back to the Prati area while allowing the works on Line C of the metro between Colosseo and Farnesina to continue.
Here are all the details of the affected routes, timings, and replacement stops.
| Line | Dates | Replacement Service | Timings | Main Bus Routes and Stops |
|---|---|---|---|---|
| 2 | From 3 August | The tram service will be fully replaced by buses. | All day | TOWARDS PIAZZA MANCINI
TOWARDS PIAZZALE FLAMINIO
|
| 3 | From 11 September
From 19 October until further notice, except on Sundays, due to roadworks on Via del Parco del Celio. | The tram service operates between Porta Maggiore and Trastevere Station. Between Porta Maggiore and Valle Giulia, the service is replaced by buses.
Tram services will be replaced by buses along the entire route due to works on Via del Parco del Celio. The last trams will depart from Porta Maggiore at 20:15 pm and from Trastevere railway station at 21:00 After these times, buses will replace trams along the entire route. | All day | TOWARDS PORTA MAGGIORE
TOWARDS VALLE GIULIA
Between Piazza del Colosseo and Piazza di Porta Capena, replacement buses will run via Via Celio Vibenna and Via di San Gregorio, stopping at the bus stops along these streets. |
| 5 | From 19 October | Tram line 514 will resume operating between Largo Preneste and Termini railway station. Bus line 19 will continue to operate between Piazza dei Gerani and Ottaviano metro station (Metro Line A), serving the section between Largo Preneste and Centocelle. | All day | |
| 14 | From 19 October | Tram line 514 has resumed operating between Largo Preneste and Termini railway station. Bus line 14BUS will operate between Largo Preneste and Viale Palmiro Togliatti | All day | TOWARDS VIALE PALMIRO TOGLIATTI
TOWARDS LARGO PRENESTE
|
| 19 |
From 12 to 24 October, from 9 p.m. until the end of service, due to road resurfacing works in the tram lane on Viale dello Scalo di San Lorenzo, | Tram service fully replaced by buses.
Buses are diverted to the side lanes. | All day | TOWARDS METRO LINE A/OTTAVIANO On Via Prenestina:
TOWARDS PIAZZA DEI GERANI From Viale Giulio Cesare:
On Via Prenestina:
|
Passengers are advised to allow extra time for their journeys and to check for further updates before travelling.
For further details on routes and timings, please visit the official ATAC website at this page.